| Assessment Year | 2000 |
|---|---|
| Principal Product | Plastic Injection Molding |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
42,000
ft2
|
| Annual Production | 13,500
lb
|
| Production Hrs. Annual | 5,046
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $62,654 | 689,918 |
kWh
|
$0.091 |
| Electricity Demand | $4,958 | 3,149 |
kW-mo/yr
|
$1.57 |
| Electricity Fees | $72,330 | - |
|
- |
| LPG | $3,777 | 334 |
MMBtu
|
$11.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,542 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,772 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $160 | $145 |
$92
1,172
kWh
|
$19
-
kW-mo/yr
|
$24 | $25 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,392 | $14,863 |
$13,076
175,264
kWh
|
$2,316
-
kW-mo/yr
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $502 | $781 |
$430
5,862
kWh
|
$72
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $405 | $525 |
$320
4,396
kWh
|
$85
-
kW-mo/yr
|
- | - | |
| 05 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $365 | $150 |
$365
4,982
kWh
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $299 | $440 |
$255
2,931
kWh
|
$44
-
kW-mo/yr
|
- | - | |
| 07 | 2.1332: Convert combustion equipment to burn natural gas | $2,419 | $295 | - | - | $2,419 | - | |
| TOTAL RECOMMENDED | $19,542 | $17,199 |
$14,538
194,607
kWh
|
$2,536
-
kW-mo/yr
|
$2,443 | $25 | ||
| TOTAL IMPLEMENTED | $18,772 | $16,524 |
$13,853
185,229
kWh
|
$2,451
-
kW-mo/yr
|
$2,443 | $25 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs