ITAC Assessment: AS0269
ITAC logo
ITAC Assessment: AS0269
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Oak Furniture
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 65,000
ft2
Annual Production 45,000
pieces
Production Hrs. Annual 2,149
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,201 439,332
kWh
Electricity Demand $3,774 2,360
kW-mo/yr
Electricity Fees $3,637 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,258 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7232: Replace existing hvac unit with high efficiency model $930 $500 $848
11,137
kWh
$82
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,234 $4,658 $901
11,723
kWh
$333
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,163 $320 $3,163
41,325
kWh
- - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $2,071 $120 - - $2,071
-
lb
-
05 4.511: Expand operations into unused space $2,860 $2,920 - - - $2,860
06 4.231: Purchase equipment instead of leasing $21,000 $28,000 - - - $21,000
TOTAL RECOMMENDED $31,258 $36,518 $4,912
64,185
kWh
$415
-
kW-mo/yr
$2,071
-
lb
$23,860
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs