| Assessment Year | 1999 |
|---|---|
| Principal Product | Manufactured Homes |
| NAICS |
n/a
|
| SIC | 2452: Prefabricated Wood Buildings and Components |
| Sales Range | $10 M to 50M |
| # of Employees | 260 |
| Plant Area |
110,000
ft2
|
| Annual Production | 1,100
pieces
|
| Production Hrs. Annual | 2,185
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $96,727 | 1,181,419 |
kWh
|
$0.082 |
| Electricity Demand | $7,922 | 4,687 |
kW-mo/yr
|
$1.69 |
| Electricity Fees | $7,554 | - |
|
- |
| Natural Gas | $6,955 | 918 |
MMBtu
|
$7.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $79,396 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $69,592 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,761 | $10,671 |
$1,596
33,705
kWh
|
$1,165
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,410 | $3,840 |
$3,410
71,512
kWh
|
- | - | - | - | - | |
| 03 | 2.7232: Replace existing hvac unit with high efficiency model | $2,133 | $2,400 |
$1,725
36,342
kWh
|
$408
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,330 | $840 |
$2,330
48,945
kWh
|
- | - | - | - | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,213 | $3,800 |
$1,652
34,584
kWh
|
$1,561
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 3.5131: Recycle white water | $14,029 | $500 | - | - |
$36
-
Tgal
|
$9,660
-
gal
|
- | $4,333 | |
| 07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $420 | $120 | - | - | - | - |
$420
-
lb
|
- | |
| 08 | 4.711: Initiate a total quality management program | $51,100 | $13,200 | - | - | - | - | - | $51,100 | |
| TOTAL RECOMMENDED | $79,396 | $35,371 |
$10,713
225,088
kWh
|
$3,134
-
kW-mo/yr
|
$36
-
Tgal
|
$9,660
-
gal
|
$420
-
lb
|
$55,433 | ||
| TOTAL IMPLEMENTED | $69,592 | $16,940 |
$4,055
85,287
kWh
|
$408
-
kW-mo/yr
|
$36
-
Tgal
|
$9,660
-
gal
|
- | $55,433 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs