Assessment Year | 1999 |
---|---|
Principal Product | Structural Steel |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
80,000
ft2
|
Annual Production | 4,000
ton
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,978 | 415,885 |
kWh
|
$0.067 |
Electricity Demand | $7,421 | 2,938 |
kW-mo/yr
|
$2.53 |
Electricity Fees | $2,285 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $351 | $375 |
$351
4,982
kWh
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,404 | $120 |
$1,160
16,120
kWh
|
$244
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $641 | $2,625 |
$549
7,620
kWh
|
$92
-
kW-mo/yr
|
- | - | - | |
04 | 3.1191: Change procedures / equipment / operating conditions | $213 | $792 |
$52
586
kWh
|
$12
-
kW-mo/yr
|
$17
-
gal
|
$132 | - | |
05 | 3.6192: Use a less expensive method of waste removal | $1,775 | $90 | - | - |
$1,775
-
gal
|
- | - | |
06 | 4.212: Adopt in-house material generation | $6,187 | $90 | - | - | - | - | $6,187 | |
TOTAL RECOMMENDED | $10,571 | $4,092 |
$2,112
29,308
kWh
|
$348
-
kW-mo/yr
|
$1,792
-
gal
|
$132 | $6,187 | ||
TOTAL IMPLEMENTED | $6,400 | $882 |
$52
586
kWh
|
$12
-
kW-mo/yr
|
$17
-
gal
|
$132 | $6,187 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs