Assessment Year | 1999 |
---|---|
Principal Product | Semiconductors |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $50 M to 100M |
# of Employees | 490 |
Plant Area |
80,000
ft2
|
Annual Production | 728,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $644,280 | 12,961,606 |
kWh
|
$0.050 |
Electricity Demand | $64,927 | 22,276 |
kW-mo/yr
|
$2.91 |
Electricity Fees | $53,104 | - |
|
- |
Natural Gas | $235,957 | 47,021 |
MMBtu
|
$5.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $293,028 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,703 | $26,778 |
$15,648
404,455
kWh
|
$6,055
-
kW-mo/yr
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,677 | $2,148 |
$1,202
31,067
kWh
|
$475
-
kW-mo/yr
|
- | - | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $3,361 | $2,700 |
$2,412
62,427
kWh
|
$949
-
kW-mo/yr
|
- | - | - | |
04 | 3.8314: Purchase high materials in returnable bulk containers | $14,376 | $15,000 | - | - |
$14,376
-
lb
|
- | - | |
05 | 4.812: Apply for investment incentives | $7,303 | $60 | - | - | - | - | $7,303 | |
06 | 4.446: Automate finishing process | $244,608 | $111,104 | - | - | - | $244,608 | - | |
TOTAL RECOMMENDED | $293,028 | $157,790 |
$19,262
497,949
kWh
|
$7,479
-
kW-mo/yr
|
$14,376
-
lb
|
$244,608 | $7,303 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs