Assessment Year | 1998 |
---|---|
Principal Product | Automated Machinery |
NAICS |
n/a
|
SIC | 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products |
Sales Range | $5 M to 10M |
# of Employees | 22 |
Plant Area |
40,000
ft2
|
Annual Production | 50
pieces
|
Production Hrs. Annual | 2,725
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,036 | 461,899 |
kWh
|
$0.063 |
Electricity Demand | $3,771 | 1,444 |
kW-mo/yr
|
$2.61 |
Electricity Fees | $3,103 | - |
|
- |
Natural Gas | $4,451 | 680 |
MMBtu
|
$6.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $138,173 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $135,468 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $324 | $525 |
$324
5,862
kWh
|
- | - | - | - | |
02 | 2.7141: Lower light fixtures in high ceiling areas | $1,398 | $4,425 |
$1,097
20,223
kWh
|
$301
-
kW-mo/yr
|
- | - | - | |
03 | 3.6192: Use a less expensive method of waste removal | $3,384 | $60 | - | - |
$3,384
-
lb
|
- | - | |
04 | 4.322: Eliminate old stock and modify inventory control | $132,000 | $48,000 | - | - | - | - | $132,000 | |
05 | 4.812: Apply for investment incentives | $900 | $60 | - | - | - | $900 | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $83 | $100 | - | - | - | $83 | - | |
07 | 4.454: Modify startup/shutdown times | $84 | $360 |
$84
15,533
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $138,173 | $53,530 |
$1,505
41,618
kWh
|
$301
-
kW-mo/yr
|
$3,384
-
lb
|
$983 | $132,000 | ||
TOTAL IMPLEMENTED | $135,468 | $48,420 |
$84
15,533
kWh
|
- |
$3,384
-
lb
|
- | $132,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs