Assessment Year | 1998 |
---|---|
Principal Product | Steel Hosereels |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
20,000
ft2
|
Annual Production | 60,000
pieces
|
Production Hrs. Annual | 4,310
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,182 | 973,329 |
kWh
|
$0.061 |
Electricity Demand | $9,112 | 3,108 |
kW-mo/yr
|
$2.93 |
Electricity Fees | $5,832 | - |
|
- |
Natural Gas | $51,412 | 9,267 |
MMBtu
|
$5.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $159,986 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $155,158 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $508 | $220 |
$351
7,034
kWh
|
$157
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $524 | $60 |
$363
7,327
kWh
|
$161
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $415 | $365 |
$415
8,499
kWh
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,226 | $8,275 |
$1,415
29,015
kWh
|
$811
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $83 | $87 |
$45
879
kWh
|
$8
-
kW-mo/yr
|
- | $15 | - | $15 | |
06 | 3.6192: Use a less expensive method of waste removal | $368 | $60 | - | - | - | - | $368 | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $47,175 | $480 | - | - | - | $47,175 | - | - | |
08 | 4.812: Apply for investment incentives | $704 | $60 | - | - | - | - | $704 | - | |
09 | 4.121: Maintain clean conditions before painting | $11,008 | $1,480 | - | - |
$1,008
-
MMBtu
|
$10,000 | - | - | |
10 | 4.514: Re-arrange equipment layout to reduce handling costs | $96,975 | $150,000 | - | - | - | $96,975 | - | - | |
TOTAL RECOMMENDED | $159,986 | $161,087 |
$2,589
52,754
kWh
|
$1,137
-
kW-mo/yr
|
$1,008
-
MMBtu
|
$154,165 | $1,072 | $15 | ||
TOTAL IMPLEMENTED | $155,158 | $151,960 | - | - |
$1,008
-
MMBtu
|
$154,150 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs