Assessment Year | 1998 |
---|---|
Principal Product | Extrusion of Aluminum Products |
NAICS |
n/a
|
SIC | 3354: Aluminum Extruded Products |
Sales Range | $50 M to 100M |
# of Employees | 375 |
Plant Area |
150,000
ft2
|
Annual Production | 36,000,000
lb
|
Production Hrs. Annual | 6,480
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,123,491 | 18,681,419 |
kWh
|
$0.060 |
Electricity Demand | $62,164 | 38,518 |
kW-mo/yr
|
$1.61 |
Electricity Fees | $80,340 | - |
|
- |
Natural Gas | $1,077,328 | 330,490 |
MMBtu
|
$3.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $151,896 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,938 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,509 | $12,941 |
$5,544
114,302
kWh
|
$1,965
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,979 | $200 |
$5,297
109,320
kWh
|
$1,682
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $16,030 | $56,554 |
$12,168
250,879
kWh
|
$3,862
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $352 | $435 |
$296
6,155
kWh
|
$56
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,538 | $16,808 |
$5,496
113,716
kWh
|
$2,042
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $14,691 | $300 |
$11,421
235,639
kWh
|
$3,270
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.7232: Replace existing hvac unit with high efficiency model | $3,284 | $6,800 |
$2,659
54,807
kWh
|
$625
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.7261: Install timers and/or thermostats | $1,094 | $1,275 |
$1,094
22,567
kWh
|
- | - | - | - | - | - | |
09 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,718 | $450 | - | - |
$1,718
-
MMBtu
|
- | - | - | - | |
10 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $859 | $150 |
$584
12,016
kWh
|
$275
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 3.6192: Use a less expensive method of waste removal | $4,584 | $60 | - | - | - |
$4,584
-
lb
|
- | - | - | |
12 | 3.4151: Minimize water usage | $945 | $400 | - | - | - | - | - | - |
$945
-
Tgal
|
|
13 | 3.7197: Use ultrasonic cleaning | $79,533 | $315,000 |
$(-4,577.0)
(-94,373)
kWh
|
$(-11,182.0)
-
kW-mo/yr
|
$23,765
-
MMBtu
|
- | $71,527 | - | - | |
14 | 4.652: Replace existing equipment with more suitable substitutes | $6,780 | $3,756 | - | - | - | - | $350 | $6,477 |
$(-47.0)
-
Tgal
|
|
TOTAL RECOMMENDED | $151,896 | $415,129 |
$39,982
825,028
kWh
|
$2,595
-
kW-mo/yr
|
$25,483
-
MMBtu
|
$4,584
-
lb
|
$71,877 | $6,477 |
$898
-
Tgal
|
||
TOTAL IMPLEMENTED | $25,938 | $57,789 |
$18,345
378,370
kWh
|
$5,875
-
kW-mo/yr
|
$1,718
-
MMBtu
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs