| Assessment Year | 1998 |
|---|---|
| Principal Product | Recycled Rubber |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 47 |
| Plant Area |
60,000
ft2
|
| Annual Production | 34,500,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $275,993 | 8,414,127 |
kWh
|
$0.033 |
| Electricity Demand | $144,851 | 16,731 |
kW-mo/yr
|
$8.66 |
| Electricity Fees | $83,303 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $204,833 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $132,745 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,248 | $4,077 |
$1,300
42,497
kWh
|
$948
-
kW-mo/yr
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $558 | $975 |
$332
10,844
kWh
|
$226
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,576 | $3,402 |
$2,852
93,200
kWh
|
$1,724
-
kW-mo/yr
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $15,653 | $26,233 |
$9,755
318,288
kWh
|
$5,898
-
kW-mo/yr
|
- | - | |
| 05 | 2.6218: Turn off equipment when not in use | $1,301 | $60 |
$811
26,377
kWh
|
$490
-
kW-mo/yr
|
- | - | |
| 06 | 3.1291: Eliminate practice of mixing waste streams | $700 | $30 | - | - |
$700
-
gal
|
- | |
| 07 | 4.451: Add additional production shift | $55,877 | $3,200 | - | - | - | $55,877 | |
| 08 | 4.231: Purchase equipment instead of leasing | $123,920 | $215,000 | - | - | - | $123,920 | |
| TOTAL RECOMMENDED | $204,833 | $252,977 |
$15,050
491,206
kWh
|
$9,286
-
kW-mo/yr
|
$700
-
gal
|
$179,797 | ||
| TOTAL IMPLEMENTED | $132,745 | $222,569 |
$4,963
162,074
kWh
|
$3,162
-
kW-mo/yr
|
$700
-
gal
|
$123,920 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs