Assessment Year | 1998 |
---|---|
Principal Product | Process Steel Plates |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 44 |
Plant Area |
71,590
ft2
|
Annual Production | 9,000
ton
|
Production Hrs. Annual | 4,769
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,736 | 788,101 |
kWh
|
$0.087 |
Electricity Demand | $5,119 | 2,985 |
kW-mo/yr
|
$1.71 |
Electricity Fees | $7,138 | - |
|
- |
Natural Gas | $6,688 | 1,131 |
MMBtu
|
$5.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $43,225 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,639 | $5,513 |
$2,953
38,101
kWh
|
$686
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $766 | $750 |
$656
8,499
kWh
|
$110
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.7122: Disconnect ballasts | $183 | $15 |
$171
2,345
kWh
|
$12
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,042 | $60 |
$884
11,430
kWh
|
$158
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.7261: Install timers and/or thermostats | $671 | $375 |
$671
8,792
kWh
|
- | - | - | - | - | - | - | |
06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $5,307 | $940 |
$3,747
48,359
kWh
|
$1,560
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 3.6192: Use a less expensive method of waste removal | $444 | $60 | - | - | - |
$444
-
lb
|
- | - | - | - | |
08 | 4.212: Adopt in-house material generation | $2,435 | $375 | - | - |
$(-12.0)
-
Tgal
|
- | - | - | $(-135.0) |
$2,582
-
Tgal
|
|
09 | 4.322: Eliminate old stock and modify inventory control | $35,483 | $960 | - | - | - | - | $1,913 | $33,570 | - | - | |
TOTAL RECOMMENDED | $49,970 | $9,048 |
$9,082
117,526
kWh
|
$2,526
-
kW-mo/yr
|
$(-12.0)
-
Tgal
|
$444
-
lb
|
$1,913 | $33,570 | $(-135.0) |
$2,582
-
Tgal
|
||
TOTAL IMPLEMENTED | $43,225 | $2,275 |
$3,747
48,359
kWh
|
$1,560
-
kW-mo/yr
|
$(-12.0)
-
Tgal
|
- | $1,913 | $33,570 | $(-135.0) |
$2,582
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs