Assessment Year | 1997 |
---|---|
Principal Product | Non-Metallic Honeycomb Material |
NAICS |
n/a
|
SIC | 2295: Coated Fabrics, Not Rubberized |
Sales Range | $10 M to 50M |
# of Employees | 47 |
Plant Area |
154,000
ft2
|
Annual Production | 1,000
thousand feet
|
Production Hrs. Annual | 4,043
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $274,277 | 7,737,398 |
kWh
|
$0.035 |
Electricity Demand | $146,736 | 15,805 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $85,512 | - |
|
- |
Natural Gas | $281,866 | 95,813 |
MMBtu
|
$2.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $188,095 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6242: Minimize operation of equipment maintained in standby condition | $63,320 | $2,400 | - | - |
$63,320
-
MMBtu
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,248 | $16,974 |
$4,062
121,630
kWh
|
$4,186
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $6,113 | $8,000 |
$2,399
74,150
kWh
|
$3,714
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,786 | $60 |
$1,179
35,463
kWh
|
$1,607
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $1,579 | - |
$777
23,447
kWh
|
$802
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,288 | $3,115 |
$545
16,413
kWh
|
$743
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $1,188 | $1,381 |
$506
14,947
kWh
|
$682
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.7135: Install occupancy sensors | $696 | $1,650 |
$463
14,654
kWh
|
$233
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.7261: Install timers and/or thermostats | $324 | $320 |
$324
13,482
kWh
|
- | - | - | - | - | - | |
10 | 3.3131: Use evaporation to concentrate material | $36,527 | $13,260 |
$(-1,363.0)
56,858
kWh
|
- | - |
$37,890
-
gal
|
- | - | - | |
11 | 3.1191: Change procedures / equipment / operating conditions | $56,857 | $66,040 | - | - | - | - |
$27,191
-
gal
|
$10,920 | $18,746 | |
12 | 4.521: Clear and rent existing space | $9,169 | $19,200 |
$3,442
104,924
kWh
|
$5,727
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $188,095 | $132,400 |
$12,334
475,968
kWh
|
$17,694
-
kW-mo/yr
|
$63,320
-
MMBtu
|
$37,890
-
gal
|
$27,191
-
gal
|
$10,920 | $18,746 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs