ITAC Assessment: AS0204
ITAC logo
ITAC Assessment: AS0204
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Non-Metallic Honeycomb Material
NAICS
n/a
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $10
M
to 50
M
# of Employees 47
Plant Area 154,000
ft2
Annual Production 1,000
thousand feet
Production Hrs. Annual 4,043
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,277 7,737,398
kWh
Electricity Demand $146,736 15,805
kW-mo/yr
Electricity Fees $85,512 -
Natural Gas $281,866 95,813
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $188,095 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.6242: Minimize operation of equipment maintained in standby condition $63,320 $2,400 - - $63,320
-
MMBtu
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,248 $16,974 $4,062
121,630
kWh
$4,186
-
kW-mo/yr
- - - - -
03 2.7232: Replace existing hvac unit with high efficiency model $6,113 $8,000 $2,399
74,150
kWh
$3,714
-
kW-mo/yr
- - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,786 $60 $1,179
35,463
kWh
$1,607
-
kW-mo/yr
- - - - -
05 2.7111: Reduce illumination to minimum necessary levels $1,579 - $777
23,447
kWh
$802
-
kW-mo/yr
- - - - -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,288 $3,115 $545
16,413
kWh
$743
-
kW-mo/yr
- - - - -
07 2.4133: Use most efficient type of electric motors $1,188 $1,381 $506
14,947
kWh
$682
-
kW-mo/yr
- - - - -
08 2.7135: Install occupancy sensors $696 $1,650 $463
14,654
kWh
$233
-
kW-mo/yr
- - - - -
09 2.7261: Install timers and/or thermostats $324 $320 $324
13,482
kWh
- - - - - -
10 3.3131: Use evaporation to concentrate material $36,527 $13,260 $(-1,363.0)
56,858
kWh
- - $37,890
-
gal
- - -
11 3.1191: Change procedures / equipment / operating conditions $56,857 $66,040 - - - - $27,191
-
gal
$10,920 $18,746
12 4.521: Clear and rent existing space $9,169 $19,200 $3,442
104,924
kWh
$5,727
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $188,095 $132,400 $12,334
475,968
kWh
$17,694
-
kW-mo/yr
$63,320
-
MMBtu
$37,890
-
gal
$27,191
-
gal
$10,920 $18,746
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs