ITAC Assessment: AS0200
ITAC logo
ITAC Assessment: AS0200
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Pressure Sensitive Labels
NAICS
n/a
SIC 2641:
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area 58,000
ft2
Annual Production 20,000
thousand feet
Production Hrs. Annual 4,950
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,802 1,675,264
kWh
Electricity Demand $11,851 4,272
kW-mo/yr
Electricity Fees $9,628 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $55,391 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,732

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7232: Replace existing hvac unit with high efficiency model $13,061 $18,500 $7,110
182,005
kWh
$5,951
-
kW-mo/yr
- - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,941 $17 $1,143
29,308
kWh
$798
-
kW-mo/yr
- - - -
03 2.7261: Install timers and/or thermostats $1,567 $1,440 $1,567
40,152
kWh
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,154 $224 $563
14,361
kWh
$591
-
kW-mo/yr
- - - -
05 2.4131: Size electric motors for peak operating efficiency $464 $621 $264
6,741
kWh
$200
-
kW-mo/yr
- - - -
06 2.7135: Install occupancy sensors $313 $300 $213
5,569
kWh
$100
-
kW-mo/yr
- - - -
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $9,346 $14,000 $(-16.0)
293
kWh
- $10,584
-
gal
$(-442.0) - $(-780.0)
08 3.6192: Use a less expensive method of waste removal $1,344 $34 - - - - $1,344 -
09 4.452: Eliminate shift $26,201 $100 $551
14,068
kWh
- - $25,650 - -
TOTAL RECOMMENDED $55,391 $35,236 $11,395
292,497
kWh
$7,640
-
kW-mo/yr
$10,584
-
gal
$25,208 $1,344 $(-780.0)
TOTAL IMPLEMENTED $38,732 $16,385 $2,929
75,615
kWh
$791
-
kW-mo/yr
$10,584
-
gal
$25,208 - $(-780.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs