| Assessment Year | 1996 |
|---|---|
| Principal Product | Cameras & Printers |
| NAICS |
n/a
|
| SIC | 3861: Photographic Equipment and Supplies |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
55,000
ft2
|
| Annual Production | 1,250
pieces
|
| Production Hrs. Annual | 4,394
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $19,528 | 622,509 |
kWh
|
$0.031 |
| Electricity Demand | $17,426 | 2,304 |
kW-mo/yr
|
$7.56 |
| Electricity Fees | $1,063 | - |
|
- |
| Natural Gas | $24,750 | 5,612 |
MMBtu
|
$4.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,007 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,110 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $859 | $859 |
$460
14,654
kWh
|
$399
-
kW-mo/yr
|
- | - | - | |
| 02 | 3.1191: Change procedures / equipment / operating conditions | $638 | $175 | - | - | - | - | $638 | |
| 03 | 2.7135: Install occupancy sensors | $164 | $100 |
$164
4,982
kWh
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,728 | $300 |
$1,775
56,565
kWh
|
$953
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.4113: Treat and reuse rinse waters | $733 | $380 | - | - | - |
$733
-
Tgal
|
- | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $1,885 | $1,050 | - | - |
$1,885
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $7,007 | $2,864 |
$2,399
76,201
kWh
|
$1,352
-
kW-mo/yr
|
$1,885
-
MMBtu
|
$733
-
Tgal
|
$638 | ||
| TOTAL IMPLEMENTED | $6,110 | $2,384 |
$2,235
71,219
kWh
|
$1,352
-
kW-mo/yr
|
$1,885
-
MMBtu
|
- | $638 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs