ITAC Assessment: AS0168
ITAC logo
ITAC Assessment: AS0168
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Aerospace Composite
NAICS
n/a
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area 80,000
ft2
Annual Production 15
ton
Production Hrs. Annual 2,080
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $251,313 4,955,745
kWh
Electricity Demand $76,682 9,920
kW-mo/yr
Natural Gas $32,893 6,270
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $73,648 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $66,332

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.6231: Utilize controls to operate equipment only when needed $490 $150 $490
9,965
kWh
- - - -
02 2.4314: Use synthetic lubricant $468 $124 $160
3,224
kWh
$49
-
kW-mo/yr
- $268
-
gal
$(-9.0)
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,596 - $861
17,585
kWh
$735
-
kW-mo/yr
- - -
04 2.7135: Install occupancy sensors $306 $300 $306
6,155
kWh
- - - -
05 2.7241: Install outside air damper / economizer on hvac unit $38,756 $1,750 $38,756
710,141
kWh
- - - -
06 2.2625: Chill water to the highest temperature possible $11,824 - $5,142
104,338
kWh
$1,534
-
kW-mo/yr
$5,148
-
MMBtu
- -
07 2.2614: Use cooling tower or economizer to replace chiller cooling $4,044 $20,000 $4,044
82,063
kWh
- - - -
08 2.7423: Reduce heat gain by window tinting $2,966 $10,750 $2,966
60,082
kWh
- - - -
09 2.4133: Use most efficient type of electric motors $3,991 $7,201 $2,043
41,325
kWh
$1,948
-
kW-mo/yr
- - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $228 - $117
2,345
kWh
$111
-
kW-mo/yr
- - -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,557 $11,870 $2,409
48,945
kWh
$2,148
-
kW-mo/yr
- - -
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,967 $8,690 $1,558
31,653
kWh
$1,409
-
kW-mo/yr
- - -
13 2.1233: Analyze flue gas for proper air/fuel ratio $1,455 $1,200 - - $1,455
-
MMBtu
- -
TOTAL RECOMMENDED $73,648 $62,035 $58,852
1,117,821
kWh
$7,934
-
kW-mo/yr
$6,603
-
MMBtu
$268
-
gal
$(-9.0)
TOTAL IMPLEMENTED $66,332 $30,985 $51,536
969,521
kWh
$7,934
-
kW-mo/yr
$6,603
-
MMBtu
$268
-
gal
$(-9.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs