Assessment Year | 1996 |
---|---|
Principal Product | Electronic Products |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $5 M to 10M |
# of Employees | 575 |
Plant Area |
105,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $219,955 | 5,310,082 |
kWh
|
$0.041 |
Electricity Demand | $79,071 | 9,924 |
kW-mo/yr
|
$7.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,517 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,921 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,627 | $3,381 |
$1,005
33,118
kWh
|
$1,622
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $145 | $137 |
$145
4,689
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $938 | - |
$397
13,189
kWh
|
$541
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $596 | $560 |
$252
8,499
kWh
|
$344
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,634 | $10,934 |
$1,024
35,170
kWh
|
$1,610
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $577 | $975 |
$577
19,050
kWh
|
- | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,000 | $19,750 | - | - |
$8,000
-
lb
|
|
TOTAL RECOMMENDED | $15,517 | $35,737 |
$3,400
113,715
kWh
|
$4,117
-
kW-mo/yr
|
$8,000
-
lb
|
||
TOTAL IMPLEMENTED | $14,921 | $35,177 |
$3,148
105,216
kWh
|
$3,773
-
kW-mo/yr
|
$8,000
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs