ITAC Assessment: AS0167
ITAC logo
ITAC Assessment: AS0167
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Electronic Products
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $5
M
to 10
M
# of Employees 575
Plant Area 105,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $219,955 5,310,082
kWh
Electricity Demand $79,071 9,924
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,517 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,921

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4133: Use most efficient type of electric motors $2,627 $3,381 $1,005
33,118
kWh
$1,622
-
kW-mo/yr
-
02 2.2511: Insulate bare equipment $145 $137 $145
4,689
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $938 - $397
13,189
kWh
$541
-
kW-mo/yr
-
04 2.4221: Install compressor air intakes in coolest locations $596 $560 $252
8,499
kWh
$344
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,634 $10,934 $1,024
35,170
kWh
$1,610
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $577 $975 $577
19,050
kWh
- -
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $8,000 $19,750 - - $8,000
-
lb
TOTAL RECOMMENDED $15,517 $35,737 $3,400
113,715
kWh
$4,117
-
kW-mo/yr
$8,000
-
lb
TOTAL IMPLEMENTED $14,921 $35,177 $3,148
105,216
kWh
$3,773
-
kW-mo/yr
$8,000
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs