ITAC Assessment: AS0153
ITAC logo
ITAC Assessment: AS0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Electronic Casings & Machined Sheetmetal Parts
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $5
M
to 10
M
# of Employees 63
Plant Area 50,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 4,875
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,231 872,802
kWh
LPG $2,398 284
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,358 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,822

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,342 $4,568 $3,342
46,014
kWh
02 2.7124: Make a practice of turning off lights when not needed $1,000 - $1,000
17,878
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $171 $360 $171
2,931
kWh
04 2.4133: Use most efficient type of electric motors $3,551 $3,779 $3,551
50,410
kWh
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $393 - $393
5,275
kWh
06 2.2514: Cover open tanks $1,521 $640 $1,521
27,843
kWh
07 2.7261: Install timers and/or thermostats $536 $1,000 $536
9,965
kWh
08 2.7232: Replace existing hvac unit with high efficiency model $3,844 $16,500 $3,844
55,393
kWh
TOTAL RECOMMENDED $14,358 $26,847 $14,358
215,709
kWh
TOTAL IMPLEMENTED $8,822 $9,347 $8,822
129,542
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs