ITAC Assessment: AS0101
ITAC logo
ITAC Assessment: AS0101
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product GROUND BEEF
NAICS
n/a
SIC 2011: Meat Packing Plants
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area
n/a
Annual Production 12,000,000
lb
Production Hrs. Annual 2,800
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,938 1,456,331
kWh
Natural Gas $16,367 3,731
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,723 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,783

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $1,735 $1,153 $1,735
19,930
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,945 - $4,945
56,858
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $610 $250 $610
7,034
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $720 $1,584 $720
8,206
kWh
- -
05 2.1233: Analyze flue gas for proper air/fuel ratio $201 $500 - $201
-
MMBtu
-
06 2.2136: Install / repair insulation on steam lines $964 $463 - $964
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $196 - $227
2,638
kWh
- $(-31.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $138 $272 $138
1,465
kWh
- -
09 2.7135: Install occupancy sensors $195 $236 $195
2,345
kWh
- -
10 2.6232: Install set-back timers $1,019 $1,005 $1,019
11,723
kWh
- -
TOTAL RECOMMENDED $10,723 $5,463 $9,589
110,199
kWh
$1,165
-
MMBtu
$(-31.0)
TOTAL IMPLEMENTED $8,783 $2,374 $7,850
90,270
kWh
$964
-
MMBtu
$(-31.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs