Assessment Year | 1990 |
---|---|
Principal Product | AEROSTRUCTURES |
NAICS |
n/a
|
SIC | 3721: Aircraft |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,100
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $274,813 | 13,611,958 |
kWh
|
$0.020 |
Natural Gas | $56,882 | 21,145 |
MMBtu
|
$2.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,225 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,637 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $10,575 | $18,500 | - |
$10,575
-
MMBtu
|
|
02 | 2.2514: Cover open tanks | $7,010 | $2,397 |
$3,553
150,938
kWh
|
$3,457
-
MMBtu
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,838 | - |
$4,838
137,749
kWh
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $630 | $832 |
$630
26,964
kWh
|
- | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,578 | $4,400 |
$3,578
-
kWh
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $594 | - |
$594
27,257
kWh
|
- | |
TOTAL RECOMMENDED | $27,225 | $26,129 |
$13,193
342,908
kWh
|
$14,032
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,637 | $19,332 |
$6,062
191,970
kWh
|
$10,575
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs