Assessment Year | 1992 |
---|---|
Principal Product | READY-MIX ASPHALT |
NAICS |
n/a
|
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $10 M to 50M |
# of Employees | 220 |
Plant Area |
n/a
|
Annual Production | 802,000
ton
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $490,128 | 5,504,103 |
kWh
|
$0.089 |
Natural Gas | $177,202 | 38,905 |
MMBtu
|
$4.55 |
Fuel Oil #2 | $2,870 | 1,030 |
MMBtu
|
$2.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $97,874 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $50,496 | $337,500 |
$57,935
562,427
kWh
|
- |
$2,875
-
MMBtu
|
$(-10,314.0) | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $23,380 | $240,000 |
$34,229
400,059
kWh
|
$(-4,848.0)
-
MMBtu
|
- | $(-6,001.0) | |
03 | 2.4133: Use most efficient type of electric motors | $4,081 | $43,663 |
$4,081
45,721
kWh
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,817 | - |
$8,817
99,062
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $514 | $200 |
$514
5,862
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $705 | $5,815 |
$783
8,792
kWh
|
- | - | $(-78.0) | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,887 | $4,292 |
$8,887
99,941
kWh
|
- | - | - | |
08 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $994 | - |
$994
9,965
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $97,874 | $631,470 |
$116,240
1,231,829
kWh
|
$(-4,848.0)
-
MMBtu
|
$2,875
-
MMBtu
|
$(-16,393.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs