Assessment Year | 1991 |
---|---|
Principal Product | METAL STAMPING |
NAICS |
n/a
|
SIC | 3429: Hardware, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
n/a
|
Annual Production | 2,400,000
pieces
|
Production Hrs. Annual | 3,328
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $22,463 | 254,103 |
kWh
|
$0.088 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,940 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $432 | $63 |
$432
4,982
kWh
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,895 | $500 |
$2,895
32,825
kWh
|
|
03 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $3,235 | $2,000 |
$3,235
36,635
kWh
|
|
04 | 2.4133: Use most efficient type of electric motors | $29 | $72 |
$29
293
kWh
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $349 | - |
$349
4,103
kWh
|
|
TOTAL RECOMMENDED | $6,940 | $2,635 |
$6,940
78,838
kWh
|
||
TOTAL IMPLEMENTED | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs