ITAC Assessment: AS0029
ITAC logo
ITAC Assessment: AS0029
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product AEROSPACE COMPONENTS
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area
n/a
Annual Production 2,500,000
pieces
Production Hrs. Annual 2,400
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,665 391,559
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,498 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,498

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $669 $97 $669
7,327
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $80 $198 $80
879
kWh
03 2.6232: Install set-back timers $390 $1,050 $390
4,396
kWh
04 2.4133: Use most efficient type of electric motors $40 $98 $40
586
kWh
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $107 - $107
1,172
kWh
06 2.4231: Reduce the pressure of compressed air to the minimum required $387 $1,000 $387
4,396
kWh
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,194 $1,500 $1,194
13,189
kWh
08 2.7422: Plant trees or shrubs near windows to shield from sunlight $3,631 $2,200 $3,631
39,859
kWh
TOTAL RECOMMENDED $6,498 $6,143 $6,498
71,804
kWh
TOTAL IMPLEMENTED $6,498 $6,143 $6,498
71,804
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs