ITAC Assessment: AS0007
ITAC logo
ITAC Assessment: AS0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product LAMINATED CIRCUIT BOARDS
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area
n/a
Annual Production 3,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,440 2,014,947
kWh
Natural Gas $19,681 3,548
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $267 $61 $267
4,103
kWh
-
02 2.7123: Keep lamps and reflectors clean $5,940 $15,120 $5,940
94,666
kWh
-
03 2.6232: Install set-back timers $2,168 $1,275 $2,168
34,584
kWh
-
04 2.4133: Use most efficient type of electric motors $393 $702 $393
6,155
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,032 $1,000 - $1,032
-
MMBtu
TOTAL RECOMMENDED $9,800 $18,158 $8,768
139,508
kWh
$1,032
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs