| Assessment Year | 2000 |
|---|---|
| Principal Product | Electrical wiring and cables |
| NAICS |
n/a
|
| SIC | 3679: Electronic Components, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
35,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,652 | 947,245 |
kWh
|
$0.034 |
| Electricity Demand | $21,321 | 2,894 |
kW-mo/yr
|
$7.37 |
| Natural Gas | $5,631 | 1,141 |
MMBtu
|
$4.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $251,536 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $250,386 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $235 | $75 |
$98
2,931
kWh
|
$137
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $551 | - |
$100
2,931
kWh
|
$451
-
kW-mo/yr
|
- | |
| 03 | 2.3212: Optimize plant power factor | $1,150 | $1,950 | - |
$1,150
-
kW-mo/yr
|
- | |
| 04 | 4.514: Re-arrange equipment layout to reduce handling costs | $249,600 | $6,949 | - | - | $249,600 | |
| TOTAL RECOMMENDED | $251,536 | $8,974 |
$198
5,862
kWh
|
$1,738
-
kW-mo/yr
|
$249,600 | ||
| TOTAL IMPLEMENTED | $250,386 | $7,024 |
$198
5,862
kWh
|
$588
-
kW-mo/yr
|
$249,600 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs