| Assessment Year | 1999 |
|---|---|
| Principal Product | Games,toys,children's vehicles |
| NAICS |
n/a
|
| SIC | 3944: Games, Toys, and Children's Vehicles, Except Dolls and Bicycles |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
234,543
ft2
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $841,182 | 27,355,510 |
kWh
|
$0.031 |
| Electricity Demand | $260,288 | 49,900 |
kW-mo/yr
|
$5.22 |
| Natural Gas | $134,326 | 42,290 |
MMBtu
|
$3.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,174 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $759 | $1,307 |
$496
16,120
kWh
|
$263
-
kW-mo/yr
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $176 | - |
$127
4,103
kWh
|
$49
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,097 | $21,814 |
$4,785
154,455
kWh
|
$2,312
-
kW-mo/yr
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $22,202 | $180 |
$7,106
229,191
kWh
|
$15,096
-
kW-mo/yr
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $4,046 | $402 |
$3,050
98,476
kWh
|
$996
-
kW-mo/yr
|
- | |
| 06 | 4.431: Train operators for maximum operating efficiency | $6,894 | $280 | - | - | $6,894 | |
| TOTAL RECOMMENDED | $41,174 | $23,983 |
$15,564
502,345
kWh
|
$18,716
-
kW-mo/yr
|
$6,894 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs