| Assessment Year | 1998 |
|---|---|
| Principal Product | Hoist and Related Equipment |
| NAICS |
n/a
|
| SIC | 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems |
| Sales Range | $50 M to 100M |
| # of Employees | 315 |
| Plant Area |
225,000
ft2
|
| Annual Production | 11,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $229,428 | 7,076,202 |
kWh
|
$0.032 |
| Electricity Demand | $227,699 | 17,114 |
kW-mo/yr
|
$13.30 |
| Natural Gas | $83,108 | 20,575 |
MMBtu
|
$4.04 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $249,050 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $33,786 | $22,860 | n/a | - |
$33,786
-
kW-mo/yr
|
- | - | - | - | - |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,967 | $250 | n/a |
$876
27,257
kWh
|
$1,091
-
kW-mo/yr
|
- | - | - | - | - |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $2,420 | $130 | n/a |
$1,077
33,705
kWh
|
$1,343
-
kW-mo/yr
|
- | - | - | - | - |
| 04 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $3,592 | $3,260 | n/a |
$3,592
213,658
kWh
|
- | - | - | - | - | - |
| 05 | 2.6218: Turn off equipment when not in use | $499 | $279 | n/a |
$459
14,361
kWh
|
- |
$40
-
MMBtu
|
- | - | - | - |
| 06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $13,190 | $8,000 | n/a |
$(-179.0)
(-2,638)
kWh
|
- | - | - |
$13,369
-
lb
|
- | - |
| 07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $46,527 | $1,000 | n/a | - | - | - |
$42,253
-
gal
|
- | $2,063 | $2,211 |
| 08 | 3.1192: Reduce scrap production | $14,997 | $18,800 | n/a |
$(-762.0)
(-10,551)
kWh
|
- |
$(-3,151.0)
-
MMBtu
|
$19,950
-
gal
|
- | $(-1,040.0) | - |
| 09 | 4.423: Move product using mechanical means | $66,072 | $3,200 | n/a | - | - | - | - | - | - | $66,072 |
| 10 | 4.513: Re-arrange equipment layout to reduce labor costs | $66,000 | $1,280 | n/a | - | - | - | - | - | - | $66,000 |
| TOTAL RECOMMENDED | $249,050 | $59,059 |
$5,063
275,792
kWh
|
$36,220
-
kW-mo/yr
|
$(-3,111.0)
-
MMBtu
|
$62,203
-
gal
|
$13,369
-
lb
|
$1,023 | $134,283 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs