| Assessment Year | 1997 |
|---|---|
| Principal Product | Men's Shoes and Boots |
| NAICS |
n/a
|
| SIC | 3143: Men's Footwear, Except Athletic |
| Sales Range | $10 M to 50M |
| # of Employees | 490 |
| Plant Area |
150,000
ft2
|
| Annual Production | 970,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $213,193 | 2,863,716 |
kWh
|
$0.074 |
| Electricity Demand | $39,335 | 10,423 |
kW-mo/yr
|
$3.77 |
| Natural Gas | $17,225 | 3,198 |
MMBtu
|
$5.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $230,611 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $171,023 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $627 | - |
$487
6,448
kWh
|
$140
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $2,309 | $278 |
$1,778
24,033
kWh
|
$531
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $754 | $420 |
$586
7,913
kWh
|
$168
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,279 | $370 |
$2,546
34,291
kWh
|
$733
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $88 | $1,230 |
$68
879
kWh
|
$20
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $954 | $402 |
$954
12,896
kWh
|
- | - | - | - | |
| 07 | 3.1192: Reduce scrap production | $22,337 | $4,500 | - | - |
$11,000
-
lb
|
- | $11,337 | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,245 | - |
$(-76.0)
(-293)
kWh
|
- |
$3,593
-
lb
|
$(-272.0) | - | |
| 09 | 4.514: Re-arrange equipment layout to reduce handling costs | $161,348 | $400,000 |
$(-1,215.0)
(-12,896)
kWh
|
- | - | $162,563 | - | |
| 10 | 4.515: Install shelves / racks to utilize unused space | $35,670 | $21,000 | - | - |
$12,996
-
lb
|
$22,674 | - | |
| TOTAL RECOMMENDED | $230,611 | $428,200 |
$5,128
73,271
kWh
|
$1,592
-
kW-mo/yr
|
$27,589
-
lb
|
$184,965 | $11,337 | ||
| TOTAL IMPLEMENTED | $171,023 | $402,298 |
$3,687
53,927
kWh
|
$1,452
-
kW-mo/yr
|
$3,593
-
lb
|
$162,291 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs