ITAC Assessment: AR0128
ITAC logo
ITAC Assessment: AR0128
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Men's Shoes and Boots
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 490
Plant Area 150,000
ft2
Annual Production 970,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,193 2,863,716
kWh
Electricity Demand $39,335 10,423
kW-mo/yr
Natural Gas $17,225 3,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $230,611 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $171,023

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $627 - $487
6,448
kWh
$140
-
kW-mo/yr
- - -
02 2.7111: Reduce illumination to minimum necessary levels $2,309 $278 $1,778
24,033
kWh
$531
-
kW-mo/yr
- - -
03 2.4221: Install compressor air intakes in coolest locations $754 $420 $586
7,913
kWh
$168
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,279 $370 $2,546
34,291
kWh
$733
-
kW-mo/yr
- - -
05 2.4133: Use most efficient type of electric motors $88 $1,230 $68
879
kWh
$20
-
kW-mo/yr
- - -
06 2.6212: Turn off equipment during breaks, reduce operating time $954 $402 $954
12,896
kWh
- - - -
07 3.1192: Reduce scrap production $22,337 $4,500 - - $11,000
-
lb
- $11,337
08 3.5315: Lease / purchase baler; sell cardboard to recycler $3,245 - $(-76.0)
(-293)
kWh
- $3,593
-
lb
$(-272.0) -
09 4.514: Re-arrange equipment layout to reduce handling costs $161,348 $400,000 $(-1,215.0)
(-12,896)
kWh
- - $162,563 -
10 4.515: Install shelves / racks to utilize unused space $35,670 $21,000 - - $12,996
-
lb
$22,674 -
TOTAL RECOMMENDED $230,611 $428,200 $5,128
73,271
kWh
$1,592
-
kW-mo/yr
$27,589
-
lb
$184,965 $11,337
TOTAL IMPLEMENTED $171,023 $402,298 $3,687
53,927
kWh
$1,452
-
kW-mo/yr
$3,593
-
lb
$162,291 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs