Assessment Year | 1997 |
---|---|
Principal Product | Fans and Shutters |
NAICS |
n/a
|
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
225,000
ft2
|
Annual Production | 250,000
pieces
|
Production Hrs. Annual | 2,216
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $126,335 | 1,511,430 |
kWh
|
$0.084 |
Electricity Demand | $31,455 | 8,212 |
kW-mo/yr
|
$3.83 |
Natural Gas | $82,919 | 18,551 |
MMBtu
|
$4.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $300,482 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $96,285 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $666 | $304 |
$666
6,448
kWh
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $3,632 | $4,205 |
$3,632
34,877
kWh
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $731 | $240 |
$731
7,034
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $734 | $170 |
$734
7,913
kWh
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $260 | $596 |
$260
2,638
kWh
|
- | - | |
06 | 2.3136: Overlap custodial services with normal day hours | $256 | - |
$256
2,931
kWh
|
- | - | |
07 | 3.1162: Use less wasteful packaging | $210 | $300 | - |
$210
-
lb
|
- | |
08 | 3.1192: Reduce scrap production | $18,493 | $4,546 | - |
$18,493
-
lb
|
- | |
09 | 4.112: Replace old machine with new automatic multi-station tool | $203,000 | $350,000 | - | - | $203,000 | |
10 | 4.513: Re-arrange equipment layout to reduce labor costs | $29,000 | $6,500 | - | - | $29,000 | |
11 | 4.112: Replace old machine with new automatic multi-station tool | $43,500 | $1,800 | - | - | $43,500 | |
TOTAL RECOMMENDED | $300,482 | $368,661 |
$6,279
61,841
kWh
|
$18,703
-
lb
|
$275,500 | ||
TOTAL IMPLEMENTED | $96,285 | $18,121 |
$5,292
51,876
kWh
|
$18,493
-
lb
|
$72,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs