ITAC Assessment: UM0445
ITAC logo
ITAC Assessment: UM0445
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Infrared thermopile detectors
NAICS 334413: Semiconductor and Related Device Manufacturing
SIC 3674: Semiconductors and Related Devices
Sales Range $5
M
to 10
M
# of Employees 54
Plant Area 30,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,354 665,920
kWh
Electricity Demand $15,782 1,324
kW-mo/yr
Natural Gas $12,918 1,407
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,581 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $118

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $790 $500 $790
8,880
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,158 $24,137 $1,752
19,684
kWh
$1,406
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $515 $2,300 $515
5,788
kWh
- -
04 2.2437: Recover waste heat from equipment $118 $500 - - $118
-
MMBtu
TOTAL RECOMMENDED $4,581 $27,437 $3,057
34,352
kWh
$1,406
-
kW-mo/yr
$118
-
MMBtu
TOTAL IMPLEMENTED $118 $500 - - $118
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs