Assessment Year | 2014 |
---|---|
Principal Product | Infrared thermopile detectors |
NAICS | 334413: Semiconductor and Related Device Manufacturing |
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $5 M to 10M |
# of Employees | 54 |
Plant Area |
30,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,354 | 665,920 |
kWh
|
$0.089 |
Electricity Demand | $15,782 | 1,324 |
kW-mo/yr
|
$11.92 |
Natural Gas | $12,918 | 1,407 |
MMBtu
|
$9.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,581 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $118 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $790 | $500 |
$790
8,880
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,158 | $24,137 |
$1,752
19,684
kWh
|
$1,406
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $515 | $2,300 |
$515
5,788
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $118 | $500 | - | - |
$118
-
MMBtu
|
|
TOTAL RECOMMENDED | $4,581 | $27,437 |
$3,057
34,352
kWh
|
$1,406
-
kW-mo/yr
|
$118
-
MMBtu
|
||
TOTAL IMPLEMENTED | $118 | $500 | - | - |
$118
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs