| Assessment Year | 1997 |
|---|---|
| Principal Product | Plastic Pipe Fittings and Valves |
| NAICS |
n/a
|
| SIC | 3084: Plastics Pipe |
| Sales Range | $10 M to 50M |
| # of Employees | 195 |
| Plant Area |
403,392
ft2
|
| Annual Production | 15,000,000
pieces
|
| Production Hrs. Annual | 6,257
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $364,687 | 19,803,048 |
kWh
|
$0.018 |
| Electricity Demand | $785,906 | 41,469 |
kW-mo/yr
|
$18.95 |
| Natural Gas | $58,241 | 11,266 |
MMBtu
|
$5.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $135,597 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,928 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $391 | $676 |
$391
21,688
kWh
|
- | - | - | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $436 | $335 |
$436
24,326
kWh
|
- | - | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $1,472 | $4,700 |
$1,472
81,770
kWh
|
- | - | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $293 | - |
$293
16,413
kWh
|
- | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,466 | $210 |
$1,466
81,477
kWh
|
- | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $261 | $100 |
$261
14,361
kWh
|
- | - | - | - | |
| 07 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $11,370 | $5,000 | - | - | - | $11,370 | - | |
| 08 | 2.2511: Insulate bare equipment | $1,556 | $392 |
$1,556
86,460
kWh
|
- | - | - | - | |
| 09 | 2.4239: Eliminate or reduce compressed air usage | $464 | $675 |
$464
25,791
kWh
|
- | - | - | - | |
| 10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $14,278 | $8,000 | - | - |
$14,278
-
lb
|
- | - | |
| 11 | 3.6124: Burn waste oil for heat | $3,610 | $6,500 | - |
$3,610
-
gal
|
- | - | - | |
| 12 | 4.112: Replace old machine with new automatic multi-station tool | $100,000 | $240,000 | - | - | - | - | $100,000 | |
| TOTAL RECOMMENDED | $135,597 | $266,588 |
$6,339
352,286
kWh
|
$3,610
-
gal
|
$14,278
-
lb
|
$11,370 | $100,000 | ||
| TOTAL IMPLEMENTED | $3,928 | $5,345 |
$3,928
218,347
kWh
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs