Assessment Year | 1997 |
---|---|
Principal Product | Continuous Snap Forms |
NAICS |
n/a
|
SIC | 2761: Manifold Business Forms |
Sales Range | $5 M to 10M |
# of Employees | 45 |
Plant Area |
80,139
ft2
|
Annual Production | 3,780,249
lb
|
Production Hrs. Annual | 4,588
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $84,440 | 3,077,081 |
kWh
|
$0.027 |
Electricity Demand | $123,711 | 7,278 |
kW-mo/yr
|
$17.00 |
Natural Gas | $23,073 | 4,466 |
MMBtu
|
$5.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $227,294 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $145,574 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $3,924 | $1,110 |
$1,451
52,755
kWh
|
$2,473
-
kW-mo/yr
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $593 | $593 |
$252
9,086
kWh
|
$341
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,749 | $210 |
$791
28,722
kWh
|
$958
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $735 | $15 |
$379
13,775
kWh
|
$356
-
kW-mo/yr
|
- | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $591 | $500 |
$69
2,638
kWh
|
$522
-
kW-mo/yr
|
- | - | |
06 | 2.3136: Overlap custodial services with normal day hours | $129 | $100 |
$129
4,689
kWh
|
- | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $81,000 | $51,950 | - | - |
$81,000
-
lb
|
- | |
08 | 3.1191: Change procedures / equipment / operating conditions | $116,819 | $18,225 | - | - |
$116,819
-
lb
|
- | |
09 | 4.431: Train operators for maximum operating efficiency | $21,754 | - | - | - | - | $21,754 | |
TOTAL RECOMMENDED | $227,294 | $72,703 |
$3,071
111,665
kWh
|
$4,650
-
kW-mo/yr
|
$197,819
-
lb
|
$21,754 | ||
TOTAL IMPLEMENTED | $145,574 | $20,153 |
$2,873
104,338
kWh
|
$4,128
-
kW-mo/yr
|
$116,819
-
lb
|
$21,754 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs