| Assessment Year | 1997 |
|---|---|
| Principal Product | Frictional Horsepawer Motors |
| NAICS |
n/a
|
| SIC | 3621: Motors and Generators |
| Sales Range | $10 M to 50M |
| # of Employees | 210 |
| Plant Area |
80,000
ft2
|
| Annual Production | 36,000
pieces
|
| Production Hrs. Annual | 6,674
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $97,893 | 2,739,742 |
kWh
|
$0.036 |
| Electricity Demand | $35,563 | 7,627 |
kW-mo/yr
|
$4.66 |
| Natural Gas | $8,862 | 2,873 |
MMBtu
|
$3.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $133,140 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $130,235 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,303 | $415 |
$1,017
34,291
kWh
|
$286
-
kW-mo/yr
|
- | - | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $560 | $186 |
$416
11,723
kWh
|
$144
-
kW-mo/yr
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $622 | $270 |
$420
11,723
kWh
|
$202
-
kW-mo/yr
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $469 | $1,050 |
$348
4,396
kWh
|
$121
-
kW-mo/yr
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $274 | - |
$187
5,275
kWh
|
$87
-
kW-mo/yr
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,231 | $100 |
$5,054
140,973
kWh
|
$1,177
-
kW-mo/yr
|
- | - | |
| 07 | 2.3136: Overlap custodial services with normal day hours | $835 | $100 |
$835
23,154
kWh
|
- | - | - | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $7,676 | - | - | - |
$7,676
-
lb
|
- | |
| 09 | 3.5311: Recover and reuse waste material | $2,070 | $1,000 | - | - |
$2,070
-
lb
|
- | |
| 10 | 4.112: Replace old machine with new automatic multi-station tool | $113,100 | $30,000 | - | - | - | $113,100 | |
| TOTAL RECOMMENDED | $133,140 | $33,121 |
$8,277
231,535
kWh
|
$2,017
-
kW-mo/yr
|
$9,746
-
lb
|
$113,100 | ||
| TOTAL IMPLEMENTED | $130,235 | $32,021 |
$7,442
208,381
kWh
|
$2,017
-
kW-mo/yr
|
$7,676
-
lb
|
$113,100 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs