ITAC Assessment: UD0904
ITAC logo
ITAC Assessment: UD0904
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Catalytic Convertors, Torque Convertors, Silencers
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 1,000
Plant Area 417,000
ft2
Annual Production 8,880,619
pieces
Production Hrs. Annual 6,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,508,825 40,397,514
kWh
Electricity Demand $717,182 75,732
kW-mo/yr
Natural Gas $206,656 38,120
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $396,971 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $147,219

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $10,181 - $6,766
183,174
kWh
$3,415
-
kW-mo/yr
- - - -
02 2.7224: Reduce space conditioning during non-working hours $6,875 - - - $6,875
-
MMBtu
- - -
03 2.7135: Install occupancy sensors $3,359 $450 $2,486
67,297
kWh
$873
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $34,024 $5,000 $24,768
670,496
kWh
$9,256
-
kW-mo/yr
- - - -
05 2.2437: Recover waste heat from equipment $33,689 $62,131 $(-759.0)
(-20,559)
kWh
$(-294.0)
-
kW-mo/yr
$34,742
-
MMBtu
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $6,892 - $5,017
135,828
kWh
$1,875
-
kW-mo/yr
- - - -
07 2.4239: Eliminate or reduce compressed air usage $777 $384 $510
13,817
kWh
$267
-
kW-mo/yr
- - - -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $66,236 $75,700 $44,887
1,215,120
kWh
$21,349
-
kW-mo/yr
- - - -
09 2.6212: Turn off equipment during breaks, reduce operating time $2,039 - $1,509
40,844
kWh
$530
-
kW-mo/yr
- - - -
10 2.2515: Use optimum thickness insulation $16,866 $20,982 $11,394
308,448
kWh
$5,961
-
kW-mo/yr
$(-489.0)
-
MMBtu
- - -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,786 $10,400 $2,786
75,415
kWh
- - - - -
12 3.3122: Use filtration, centrifuging to remove contaminants $96,196 $72,000 $(-1,643.0)
(-44,468)
kWh
$(-3,125.0)
-
kW-mo/yr
- $99,494
-
gal
$1,470 -
13 3.4111: Use closed cycle process to minimize waste water production $69,423 $62,000 $(-2,947.0)
(-79,772)
kWh
$(-4,205.0)
-
kW-mo/yr
- $76,575
-
gal
- -
14 3.5248: Separate and recycle scrap metal to foundry or for sale $47,628 $1,300 - - - - - $47,628
TOTAL RECOMMENDED $396,971 $310,347 $94,774
2,565,640
kWh
$35,902
-
kW-mo/yr
$41,128
-
MMBtu
$176,069
-
gal
$1,470 $47,628
TOTAL IMPLEMENTED $147,219 $112,532 $98,104
2,655,778
kWh
$42,729
-
kW-mo/yr
$6,386
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs