Assessment Year | 1996 |
---|---|
Principal Product | Aluminum Foil |
NAICS |
n/a
|
SIC | 3353: Aluminum Sheet, Plate, and Foil |
Sales Range | $50 M to 100M |
# of Employees | 206 |
Plant Area |
179,500
ft2
|
Annual Production | 44,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $403,526 | 19,221,278 |
kWh
|
$0.021 |
Electricity Demand | $563,384 | 33,238 |
kW-mo/yr
|
$16.95 |
Natural Gas | $471,101 | 148,651 |
MMBtu
|
$3.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,121 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,044 | $1,143 |
$1,569
74,736
kWh
|
$2,475
-
kW-mo/yr
|
- | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $6,354 | $2,920 |
$2,893
137,749
kWh
|
$3,461
-
kW-mo/yr
|
- | |
03 | 2.4234: Cool compressor air intake with heat exchanger | $13,886 | $13,040 |
$6,943
233,001
kWh
|
$6,943
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $3,537 | $200 |
$1,581
75,322
kWh
|
$1,956
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,300 | - |
$1,668
79,426
kWh
|
$2,632
-
kW-mo/yr
|
- | |
06 | 3.7311: Maintain machines to reduce leaks | $7,300 | $600 | - | - |
$7,300
-
gal
|
|
TOTAL RECOMMENDED | $39,421 | $17,903 |
$14,654
600,234
kWh
|
$17,467
-
kW-mo/yr
|
$7,300
-
gal
|
||
TOTAL IMPLEMENTED | $35,121 | $17,903 |
$12,986
520,808
kWh
|
$14,835
-
kW-mo/yr
|
$7,300
-
gal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs