ITAC Assessment: MA0761
ITAC logo
ITAC Assessment: MA0761
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Fresh and frozen fish items
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 12,000
ft2
Annual Production 7,000,000
lb
Production Hrs. Annual 4,160
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,947 1,458,600
kWh
Electricity Demand $22,502 5,740
kW-mo/yr
Electricity Fees $2,400 -
Natural Gas $68,843 5,101
MMBtu
Waste Disposal Costs
Water Usage $15,763 2,914
Tgal
TOTAL YEARLY COSTS $323,455
RECOMMENDED SAVINGS* $41,570 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings
01 2.2622: Replace existing chiller with high efficiency model $22,997 $134,000 $22,997
156,442
kWh
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,889 $2,685 $7,889
53,665
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,969 $6,409 $5,969
40,606
kWh
- - -
04 3.4151: Minimize water usage $3,035 $4,050 $(-200.0)
(-1,359)
kWh
- - $3,235
-
Tgal
05 2.2122: Install / repair insulation on condensate lines $864 $342 - - $864
-
MMBtu
-
06 2.3212: Optimize plant power factor $816 $2,000 - $816
-
kW-mo/yr
- -
TOTAL RECOMMENDED $41,570 $149,486 $36,655
249,354
kWh
$816
-
kW-mo/yr
$864
-
MMBtu
$3,235
-
Tgal
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs