Assessment Year | 1996 |
---|---|
Principal Product | Canned Soft Drinks |
NAICS |
n/a
|
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
80,000
ft2
|
Annual Production | 18,000,000
pieces
|
Production Hrs. Annual | 5,214
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,271 | 4,460,434 |
kWh
|
$0.040 |
Electricity Demand | $89,399 | 11,777 |
kW-mo/yr
|
$7.59 |
Natural Gas | $26,245 | 6,948 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,329 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,658 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,003 | $416 |
$670
16,706
kWh
|
$333
-
kW-mo/yr
|
- | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $10,072 | $9,295 |
$6,999
174,971
kWh
|
$3,073
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $924 | $500 |
$643
16,120
kWh
|
$281
-
kW-mo/yr
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,771 | - |
$3,321
82,943
kWh
|
$1,450
-
kW-mo/yr
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $3,599 | $6,030 |
$2,292
57,444
kWh
|
$1,307
-
kW-mo/yr
|
- | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $11,960 | $8,000 | - | - |
$11,960
-
lb
|
|
TOTAL RECOMMENDED | $32,329 | $24,241 |
$13,925
348,184
kWh
|
$6,444
-
kW-mo/yr
|
$11,960
-
lb
|
||
TOTAL IMPLEMENTED | $18,658 | $8,916 |
$4,634
115,769
kWh
|
$2,064
-
kW-mo/yr
|
$11,960
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs