ITAC Assessment: AR0090
ITAC logo
ITAC Assessment: AR0090
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Canned Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 80,000
ft2
Annual Production 18,000,000
pieces
Production Hrs. Annual 5,214
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,271 4,460,434
kWh
Electricity Demand $89,399 11,777
kW-mo/yr
Natural Gas $26,245 6,948
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,329 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,658

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,003 $416 $670
16,706
kWh
$333
-
kW-mo/yr
-
02 2.7111: Reduce illumination to minimum necessary levels $10,072 $9,295 $6,999
174,971
kWh
$3,073
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $924 $500 $643
16,120
kWh
$281
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,771 - $3,321
82,943
kWh
$1,450
-
kW-mo/yr
-
05 2.4133: Use most efficient type of electric motors $3,599 $6,030 $2,292
57,444
kWh
$1,307
-
kW-mo/yr
-
06 3.5315: Lease / purchase baler; sell cardboard to recycler $11,960 $8,000 - - $11,960
-
lb
TOTAL RECOMMENDED $32,329 $24,241 $13,925
348,184
kWh
$6,444
-
kW-mo/yr
$11,960
-
lb
TOTAL IMPLEMENTED $18,658 $8,916 $4,634
115,769
kWh
$2,064
-
kW-mo/yr
$11,960
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs