Assessment Year | 1995 |
---|---|
Principal Product | Pork Sausage |
NAICS |
n/a
|
SIC | 2011: Meat Packing Plants |
Sales Range | $50 M to 100M |
# of Employees | 225 |
Plant Area |
500,000
ft2
|
Annual Production | 53,000,000
lb
|
Production Hrs. Annual | 4,589
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $634,690 | 9,426,436 |
kWh
|
$0.067 |
Natural Gas | $105,162 | 35,360 |
MMBtu
|
$2.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $156,921 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $84,229 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,565 | $350 | - |
$1,565
-
MMBtu
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $940 | $300 |
$940
13,189
kWh
|
- | - | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $3,952 | $6,280 |
$3,952
62,134
kWh
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,148 | $4,243 |
$5,148
82,943
kWh
|
- | - | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $9,630 | $758 |
$9,630
138,628
kWh
|
- | - | - | - | - | |
06 | 2.1116: Improve combustion control capability | $597 | - | - |
$597
-
MMBtu
|
- | - | - | - | |
07 | 2.2135: Repair and eliminate steam leaks | $2,197 | $800 | - |
$2,197
-
MMBtu
|
- | - | - | - | |
08 | 2.2628: Utilize a less expensive cooling method | $2,520 | $2,092 |
$2,520
74,150
kWh
|
- | - | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,761 | $50 |
$1,761
24,326
kWh
|
- | - | - | - | - | |
10 | 2.4227: Use compressor air filters | $17,452 | $50 |
$17,452
241,501
kWh
|
- | - | - | - | - | |
11 | 2.3212: Optimize plant power factor | $25,970 | $18,765 |
$25,970
-
kWh
|
- | - | - | - | - | |
12 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $38,310 | $3,000 | - | - | - |
$38,310
-
lb
|
- | - | |
13 | 3.6113: Remove sludge from tanks on a regular basis | $46,125 | $20,000 | - | - | - | - |
$46,125
-
lb
|
- | |
14 | 3.4154: Eliminate leaks in water lines and valves | $754 | $200 | - | - |
$127
-
Tgal
|
- | - |
$627
-
Tgal
|
|
TOTAL RECOMMENDED | $156,921 | $56,888 |
$67,373
636,871
kWh
|
$4,359
-
MMBtu
|
$127
-
Tgal
|
$38,310
-
lb
|
$46,125
-
lb
|
$627
-
Tgal
|
||
TOTAL IMPLEMENTED | $84,229 | $18,123 |
$41,403
636,871
kWh
|
$3,762
-
MMBtu
|
$127
-
Tgal
|
$38,310
-
lb
|
- |
$627
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs