Assessment Year | 1995 |
---|---|
Principal Product | Fabricated Structural Steel |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
216,000
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 4,589
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $157,062 | 1,933,763 |
kWh
|
$0.081 |
Natural Gas | $31,262 | 7,210 |
MMBtu
|
$4.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,591 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,329 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,270 | $1,370 |
$3,270
27,550
kWh
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $2,684 | $4,060 |
$2,684
24,326
kWh
|
- | - | |
03 | 2.3136: Overlap custodial services with normal day hours | $2,262 | - |
$2,262
62,720
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $739 | $150 |
$739
9,965
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,404 | $500 |
$5,404
73,564
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $1,363 | $2,380 |
$1,363
16,999
kWh
|
- | - | |
07 | 2.7231: Use radiant heater for spot heating | $10,669 | $10,000 | - |
$10,669
-
MMBtu
|
- | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $13,200 | $7,000 | - | - |
$13,200
-
lb
|
|
TOTAL RECOMMENDED | $39,591 | $25,460 |
$15,722
215,124
kWh
|
$10,669
-
MMBtu
|
$13,200
-
lb
|
||
TOTAL IMPLEMENTED | $37,329 | $25,460 |
$13,460
152,404
kWh
|
$10,669
-
MMBtu
|
$13,200
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs