ITAC Assessment: IA0264
ITAC logo
ITAC Assessment: IA0264
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product EPS, wooden pallets
NAICS
n/a
SIC 2448: Wood Pallets and Skids
Sales Range $10
M
to 50
M
# of Employees 224
Plant Area 297,280
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $217,254 4,896,681
kWh
Electricity Demand $70,186 12,756
kW-mo/yr
Natural Gas $425,708 95,872
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $547,437 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,489

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,722 $173 $3,308
111,365
kWh
$2,414
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $4,073 $780 $2,326
78,318
kWh
$1,747
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,730 $44 $2,061
69,381
kWh
$1,669
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,676 - $3,151
106,106
kWh
$2,525
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,239 $5,199 $1,171
39,442
kWh
$1,068
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $328 $599 $328
11,059
kWh
- - -
07 2.4133: Use most efficient type of electric motors $1,091 - $624
21,005
kWh
$467
-
kW-mo/yr
- -
08 3.2123: Convert to high volume low pressure (hvlp) paint guns $303,062 $2,050 - - - $303,062
09 4.423: Move product using mechanical means $177,056 $100,000 $(-830.0)
(-27,930)
kWh
- $68,640 $109,246
10 3.5248: Separate and recycle scrap metal to foundry or for sale $44,460 $8,000 - - $(-15,600.0) $60,060
TOTAL RECOMMENDED $547,437 $116,845 $12,139
408,746
kWh
$9,890
-
kW-mo/yr
$53,040 $472,368
TOTAL IMPLEMENTED $12,489 $173 $7,083
238,476
kWh
$5,406
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs