| Assessment Year | 1994 |
|---|---|
| Principal Product | Boilers |
| NAICS |
n/a
|
| SIC | 3440: |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
146,739
ft2
|
| Annual Production | 500
ton
|
| Production Hrs. Annual | 5,214
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $169,385 | 2,439,918 |
kWh
|
$0.069 |
| Natural Gas | $63,512 | 15,051 |
MMBtu
|
$4.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $52,696 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $16,260 | $6,000 |
$16,260
-
kWh
|
|
| 02 | 2.2515: Use optimum thickness insulation | $855 | $100 |
$855
12,309
kWh
|
|
| 03 | 2.3212: Optimize plant power factor | $20,139 | $9,600 |
$20,139
-
kWh
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,558 | $150 |
$1,558
22,567
kWh
|
|
| 05 | 2.3512: De-energize excess transformer capacity | $3,017 | $5,760 |
$3,017
19,930
kWh
|
|
| 06 | 2.4221: Install compressor air intakes in coolest locations | $794 | $300 |
$794
11,430
kWh
|
|
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $6,740 | $790 |
$6,740
97,011
kWh
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,386 | $822 |
$1,386
19,930
kWh
|
|
| 09 | 2.6218: Turn off equipment when not in use | $1,947 | - |
$1,947
28,136
kWh
|
|
| TOTAL RECOMMENDED | $52,696 | $23,522 |
$52,696
211,313
kWh
|
||
| TOTAL IMPLEMENTED | $52,696 | $23,522 |
$52,696
211,313
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs