ITAC Assessment: MI0171
ITAC logo
ITAC Assessment: MI0171
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product plastic piping
NAICS 326122: Plastics Pipe and Pipe Fitting Manufacturing
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 398
Plant Area 100,000
ft2
Annual Production 3,500,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Puerto Rico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,331,949 12,876,600
kWh
Electricity Demand $250,588 31,129
kW-mo/yr
Electricity Fees $5,400 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $586,599 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2622: Replace existing chiller with high efficiency model $170,598 $351,000 $157,834
1,099,123
kWh
$12,764
-
kW-mo/yr
02 2.2136: Install / repair insulation on steam lines $131,514 $7,800 $121,586
846,702
kWh
$9,928
-
kW-mo/yr
03 2.4322: Use or replace with energy efficient substitutes $110,098 $168,305 $101,859
709,234
kWh
$8,239
-
kW-mo/yr
04 2.7142: Utilize higher efficiency lamps and/or ballasts $101,069 $53,922 $93,644
652,111
kWh
$7,425
-
kW-mo/yr
05 2.6218: Turn off equipment when not in use $42,003 $860 $38,917
271,009
kWh
$3,086
-
kW-mo/yr
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,317 $1,210 $26,959
187,740
kWh
$4,358
-
kW-mo/yr
TOTAL RECOMMENDED $586,599 $583,097 $540,799
3,765,919
kWh
$45,800
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs