ITAC Assessment: AR0005
ITAC logo
ITAC Assessment: AR0005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Hardwood Cabinet Doors
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 90,000
ft2
Annual Production 1,512,000
pieces
Production Hrs. Annual 2,086
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $224,834 2,188,746
kWh
Natural Gas $5,661 1,228
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,894 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,894

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $2,808 $7,910 $2,808
27,257
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,193 $527 $2,193
21,395
kWh
03 2.7111: Reduce illumination to minimum necessary levels $5,869 $2,810 $5,869
57,151
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,569 $120 $2,569
24,912
kWh
05 2.4221: Install compressor air intakes in coolest locations $455 $120 $455
4,396
kWh
TOTAL RECOMMENDED $13,894 $11,487 $13,894
135,111
kWh
TOTAL IMPLEMENTED $13,894 $11,487 $13,894
135,111
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs