ITAC Assessment: AM0998
ITAC logo
ITAC Assessment: AM0998
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Pressure Treated Lumber
NAICS 321114: Wood Preservation
SIC 2491: Wood Preserving
Sales Range $100
M
to 500
M
# of Employees 60
Plant Area 207,000
ft2
Annual Production 229,000
thousand feet
Production Hrs. Annual 6,044
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,981 1,121,894
kWh
Electricity Demand $41,715 3,558
kW-mo/yr
Electricity Fees $8,815 -
Natural Gas $22,136 1,768
MMBtu
Waste Disposal Costs
Water Usage $13,150 1,982
Tgal
Water Disposal $9,802 1,918
Tgal
TOTAL YEARLY COSTS $136,599
RECOMMENDED SAVINGS* $62,895 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $5,250 $2,300 - - $1,050 - - - - $4,200
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,510 $390 $1,050
28,690
kWh
$460
-
kW-mo/yr
- - - - - -
03 3.4155: Meter waste water $9,080 $2,650 - - - - - $9,080
-
Tgal
- -
04 2.4239: Eliminate or reduce compressed air usage $685 $650 $685
18,770
kWh
- - - - - - -
05 2.1131: Repair faulty insulation in furnaces, boilers, etc $4,220 $15,300 - - - $4,220
-
MMBtu
- - - -
06 3.4159: Replace treated water with well / surface water $27,960 $148,250 - - - - $23,000
-
Tgal
- $4,960 -
07 2.4226: Use / purchase optimum sized compressor $2,050 $13,500 $1,250
34,350
kWh
$800
-
kW-mo/yr
- - - - - -
08 2.9114: Use solar heat to make electricty $12,140 $350,280 $12,140
300,950
kWh
- - - - - - -
TOTAL RECOMMENDED $62,895 $533,320 $15,125
382,760
kWh
$1,260
-
kW-mo/yr
$1,050 $4,220
-
MMBtu
$23,000
-
Tgal
$9,080
-
Tgal
$4,960 $4,200
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs