Assessment Year | 2025 |
---|---|
Principal Product | Structural Steel |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $100 M to 500M |
# of Employees | 90 |
Plant Area |
70,000
ft2
|
Annual Production | 7,500
ton
|
Production Hrs. Annual | 5,699
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $59,300 | 718,310 |
kWh
|
$0.083 | |
Electricity Demand | $28,244 | 3,563 |
kW-mo/yr
|
$7.93 | |
Electricity Fees | $12,437 | - |
|
- | |
Natural Gas | $1,070 | 93 |
MMBtu
|
$11.49 | |
Waste Disposal Costs | |||||
Water Usage | $6,702 | 1,112 |
Tgal
|
$6.03 | |
TOTAL YEARLY COSTS | $107,753 | ||||
RECOMMENDED SAVINGS* | $102,664 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $8,340 | $2,220 |
$6,200
74,500
kWh
|
- | $2,140 | |
02 | 2.8121: Apply for tax-free status for energy purchases | $23,920 | $15,000 | - | - | $23,920 | |
03 | 2.4224: Upgrade controls on compressors | $5,160 | $25,000 |
$4,180
50,300
kWh
|
$980
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,200 | $2,449 |
$3,160
38,000
kWh
|
$678
-
kW-mo/yr
|
$362 | |
05 | 2.3212: Optimize plant power factor | $2,920 | $3,290 | - |
$2,920
-
kW-mo/yr
|
- | |
06 | 2.7145: Install skylights | $1,950 | $6,536 |
$1,950
23,400
kWh
|
- | - | |
07 | 2.4314: Use synthetic lubricant | $862 | $406 |
$262
3,160
kWh
|
$600
-
kW-mo/yr
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $312 | - |
$145
1,750
kWh
|
$167
-
kW-mo/yr
|
- | |
09 | 2.9114: Use solar heat to make electricty | $55,000 | $363,450 |
$55,000
655,000
kWh
|
- | - | |
TOTAL RECOMMENDED | $102,664 | $418,351 |
$70,897
846,110
kWh
|
$5,345
-
kW-mo/yr
|
$26,422 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs