| Assessment Year | 2024 |
|---|---|
| Principal Product | Chemical catalysts |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | greater than $500 M |
| # of Employees | 133 |
| Plant Area |
188,000
ft2
|
| Annual Production | 87,600,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $552,000 | 16,851,600 |
kWh
|
$0.033 | |
| Electricity Demand | $303,600 | 36,240 |
kW-mo/yr
|
$8.38 | |
| Electricity Fees | $65,940 | - |
|
- | |
| Natural Gas | $515,520 | 193,920 |
MMBtu
|
$2.66 | |
| Waste Disposal Costs | |||||
| Water Usage | $26,800 | 3,630 |
Tgal
|
$7.38 | |
| TOTAL YEARLY COSTS | $1,463,860 | ||||
| RECOMMENDED SAVINGS* | $217,029 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $63,000 | $15,000 | - | - | $36,000 | $27,000 | |
| 02 | 2.3212: Optimize plant power factor | $47,464 | $107,580 | - |
$47,464
-
kW-mo/yr
|
- | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $90,235 | $351,150 |
$53,460
1,619,990
kWh
|
$36,775
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $305 | $1,440 |
$305
9,240
kWh
|
- | - | - | |
| 05 | 2.9114: Use solar heat to make electricty | $16,025 | $450,534 |
$16,025
485,584
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $217,029 | $925,704 |
$69,790
2,114,814
kWh
|
$84,239
-
kW-mo/yr
|
$36,000 | $27,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs