ITAC Assessment: AM0937
ITAC logo
ITAC Assessment: AM0937
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Chemical catalysts
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range greater than $500
M
# of Employees 133
Plant Area 188,000
ft2
Annual Production 87,600,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $552,000 16,851,600
kWh
Electricity Demand $303,600 36,240
kW-mo/yr
Electricity Fees $65,940 -
Natural Gas $515,520 193,920
MMBtu
Waste Disposal Costs
Water Usage $26,800 3,630
Tgal
TOTAL YEARLY COSTS $1,463,860
RECOMMENDED SAVINGS* $217,029 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $63,000 $15,000 - - $36,000 $27,000
02 2.3212: Optimize plant power factor $47,464 $107,580 - $47,464
-
kW-mo/yr
- -
03 2.4226: Use / purchase optimum sized compressor $90,235 $351,150 $53,460
1,619,990
kWh
$36,775
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $305 $1,440 $305
9,240
kWh
- - -
05 2.9114: Use solar heat to make electricty $16,025 $450,534 $16,025
485,584
kWh
- - -
TOTAL RECOMMENDED $217,029 $925,704 $69,790
2,114,814
kWh
$84,239
-
kW-mo/yr
$36,000 $27,000
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs