ITAC Assessment: SF0244
ITAC logo
ITAC Assessment: SF0244
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Juice
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $100
M
to 500
M
# of Employees 185
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 5,200
hrs
Location (State) California
View Case Study

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $630,508 6,488,640
kWh
Electricity Demand $175,474 14,407
kW-mo/yr
Natural Gas $201,845 39,391
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $653,493 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $275,072

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.6241: Reduce temperature of process equipment when on standby $31,136 $7,960 $31,136
293,342
kWh
- - - -
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $107,810 $50,000 $107,810
1,015,713
kWh
- - - -
03 2.2437: Recover waste heat from equipment $36,936 $19,350 - - $36,936
-
MMBtu
- -
04 2.5123: Reduce fluid flow rates $31,494 $16,627 $31,494
274,197
kWh
- - - -
05 2.7135: Install occupancy sensors $2,185 $1,200 $2,185
16,087
kWh
- - - -
06 2.4133: Use most efficient type of electric motors $6,304 $4,110 $6,304
48,843
kWh
- - - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $21,274 $17,580 - - $21,274
-
MMBtu
- -
08 2.1241: Reduce excessive boiler blowdown $6,671 $6,000 - - $6,671
-
MMBtu
- -
09 2.7132: Install timers on light switches in little used areas $2,672 $2,500 $2,672
17,682
kWh
- - - -
10 2.1121: Use insulation in furnaces to facilitate heating / cooling $319 $393 - - $319
-
MMBtu
- -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $3,487 $14,055 $3,487
25,328
kWh
- - - -
12 3.4113: Treat and reuse rinse waters $218,183 $18,705 n/a - - - $218,183
-
lb
-
13 2.3132: Recharge batteries on during off-peak demand periods $8,739 - - $8,739 - - -
14 2.3212: Optimize plant power factor $2,389 $3,651 - $2,389 - - -
15 2.8114: Change rate schedules or other changes in utility service $72,375 $160,000 - $72,375 - - -
16 4.441: Install automatic packing equipment $101,519 $350,000 - - - - $101,519
TOTAL RECOMMENDED $653,493 $672,131 $185,088
1,691,192
kWh
$83,503 $65,200
-
MMBtu
$218,183
-
lb
$101,519
TOTAL IMPLEMENTED $275,072 $444,317 $145,608
1,338,753
kWh
- $27,945
-
MMBtu
- $101,519
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs