ITAC Assessment: AM0920
ITAC logo
ITAC Assessment: AM0920
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product School students
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range $1
M
to 5
M
# of Employees 32
Plant Area 66,250
ft2
Annual Production 100
units
Production Hrs. Annual 3,377
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,300 548,240
kWh
Electricity Demand $39,771 3,003
kW-mo/yr
Natural Gas $8,650 818
MMBtu
TOTAL YEARLY COSTS $71,721
RECOMMENDED SAVINGS* $33,701 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $903 $35,477 $561
13,208
kWh
- $342
-
MMBtu
02 2.9114: Use solar heat to make electricty $20,630 $460,200 $18,365
432,124
kWh
$2,265
-
kW-mo/yr
-
03 2.2625: Chill water to the highest temperature possible $6,640 $7,500 $4,398
103,494
kWh
- $2,242
-
MMBtu
04 2.1132: Repair faulty louvers and dampers $4,125 $9,000 $190
4,462
kWh
- $3,935
-
MMBtu
05 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $1,403 $1,000 $335
7,867
kWh
- $1,068
-
MMBtu
TOTAL RECOMMENDED $33,701 $513,177 $23,849
561,155
kWh
$2,265
-
kW-mo/yr
$7,587
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs