ITAC Assessment: AM0919
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product School students
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range $1
M
to 5
M
# of Employees 34
Plant Area 72,881
ft2
Annual Production 100
units
Production Hrs. Annual 3,377
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,233 517,056
kWh
Electricity Demand $45,010 3,415
kW-mo/yr
Natural Gas $7,316 712
MMBtu
TOTAL YEARLY COSTS $74,559
RECOMMENDED SAVINGS* $36,062 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,964 $20,366 $5,270
122,562
kWh
$5,694
-
kW-mo/yr
-
02 2.9114: Use solar heat to make electricty $19,780 $468,000 - $19,780
-
kW-mo/yr
-
03 2.5123: Reduce fluid flow rates $1,498 $3,000 $1,498
34,847
kWh
- -
04 3.4154: Eliminate leaks in water lines and valves $3,503 $2,500 $2,301
53,519
kWh
- $1,202
-
MMBtu
05 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $317 $1,000 $70
1,630
kWh
- $247
-
MMBtu
TOTAL RECOMMENDED $36,062 $494,866 $9,139
212,558
kWh
$25,474
-
kW-mo/yr
$1,449
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs