| Assessment Year | 2023 |
|---|---|
| Principal Product | Custom metal products |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $1 M to 5M |
| # of Employees | 135 |
| Plant Area |
92,000
ft2
|
| Annual Production | 1,150,000
pieces
|
| Production Hrs. Annual | 6,440
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $114,214 | 1,425,000 |
kWh
|
$0.080 |
| Electricity Demand | $29,704 | 3,975 |
kW-mo/yr
|
$7.47 |
| Electricity Fees | $11,935 | - |
|
- |
| Natural Gas | $11,933 | 783 |
MMBtu
|
$15.24 |
| TOTAL YEARLY COSTS | $167,786 | |||
| RECOMMENDED SAVINGS* | $33,725 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,355 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $22,785 | $7,000 | - | - | $11,393 | - | $11,392 | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $1,370 | $900 |
$1,370
17,100
kWh
|
- | - | - | - | |
| 03 | 2.7135: Install occupancy sensors | $1,130 | $460 |
$1,130
14,180
kWh
|
- | - | - | - | |
| 04 | 2.4157: Establish a predictive maintenance program | $2,630 | $4,160 |
$1,765
22,070
kWh
|
- | - | $865 | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,920 | $15 |
$3,240
40,470
kWh
|
$680
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $965 | $15 |
$770
9,585
kWh
|
$195
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $925 | $500 |
$790
9,830
kWh
|
$135
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $33,725 | $13,050 |
$9,065
113,235
kWh
|
$1,010
-
kW-mo/yr
|
$11,393 | $865 | $11,392 | ||
| TOTAL IMPLEMENTED | $32,355 | $12,150 |
$7,695
96,135
kWh
|
$1,010
-
kW-mo/yr
|
$11,393 | $865 | $11,392 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs