Assessment Year | 2022 |
---|---|
Principal Product | Treated Waste Water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 4 |
Plant Area |
484,000
ft2
|
Annual Production | 1,300
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $71,760 | 1,823,402 |
kWh
|
$0.039 | |
Electricity Demand | $54,227 | 4,210 |
kW-mo/yr
|
$12.88 | |
Waste Disposal Costs | |||||
Water Usage | $18,865 | 7,275,100 |
Tgal
|
$0.003 | |
TOTAL YEARLY COSTS | $144,852 | ||||
RECOMMENDED SAVINGS* | $5,393 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $5,283 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4156: Establish a preventative maintenance program | $4,317 | $4,220 |
$4,047
103,766
kWh
|
- | - | $270 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $966 | $3,411 |
$1,132
29,038
kWh
|
- | - | $(-166.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $110 | $37 |
$9
237
kWh
|
$5
-
kW-mo/yr
|
$64 | $32 | |
TOTAL RECOMMENDED | $5,393 | $7,668 |
$5,188
133,041
kWh
|
$5
-
kW-mo/yr
|
$64 | $136 | ||
TOTAL IMPLEMENTED | $5,283 | $7,631 |
$5,179
132,804
kWh
|
- | - | $104 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs