ITAC Assessment: AM0842
ITAC logo
ITAC Assessment: AM0842
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Treated Waste Water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 4
Plant Area 484,000
ft2
Annual Production 1,300
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $71,760 1,823,402
kWh
Electricity Demand $54,227 4,210
kW-mo/yr
Waste Disposal Costs
Water Usage $18,865 7,275,100
Tgal
TOTAL YEARLY COSTS $144,852
RECOMMENDED SAVINGS* $5,393 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,283

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4156: Establish a preventative maintenance program $4,317 $4,220 $4,047
103,766
kWh
- - $270
02 2.7142: Utilize higher efficiency lamps and/or ballasts $966 $3,411 $1,132
29,038
kWh
- - $(-166.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $110 $37 $9
237
kWh
$5
-
kW-mo/yr
$64 $32
TOTAL RECOMMENDED $5,393 $7,668 $5,188
133,041
kWh
$5
-
kW-mo/yr
$64 $136
TOTAL IMPLEMENTED $5,283 $7,631 $5,179
132,804
kWh
- - $104
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs