Assessment Year | 2019 |
---|---|
Principal Product | Water Pipes |
NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $50 M to 100M |
# of Employees | 114 |
Plant Area |
4,200,000
ft2
|
Annual Production | 15,000
ton
|
Production Hrs. Annual | 4,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $266,628 | 3,145,485 |
kWh
|
$0.085 |
Electricity Demand | $192,157 | 12,694 |
kW-mo/yr
|
$15.14 |
Electricity Fees | $17,186 | - |
|
- |
TOTAL YEARLY COSTS | $475,971 | |||
RECOMMENDED SAVINGS* | $52,471 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,546 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $28,925 | $62,407 |
$19,282
227,384
kWh
|
$9,643
-
kW-mo/yr
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,727 | - |
$9,727
114,704
kWh
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $11,229 | $21,116 |
$7,744
91,319
kWh
|
$3,485
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,737 | $1,300 |
$1,561
18,411
kWh
|
$176
-
kW-mo/yr
|
|
05 | 2.7134: Use photocell controls | $853 | $1,600 |
$853
10,064
kWh
|
- | |
TOTAL RECOMMENDED | $52,471 | $86,423 |
$39,167
461,882
kWh
|
$13,304
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $23,546 | $24,016 |
$19,885
234,498
kWh
|
$3,661
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs